Agenda Item X
Report to: |
Cabinet
|
Date of meeting:
|
30 September 2021 |
By: |
Director of Communities, Economy and Transport
|
Title: |
Introduction of a Department of Transport approved Lane Rental Scheme in East Sussex for works on the highway
|
Purpose: |
To set out how a Lane Rental scheme could be implemented to reduce work durations on the most congested roads in the county, improve planning and coordination of works
|
RECOMMENDATIONS: Cabinet are recommended to:
(1) Note the benefits of introducing a Lane Rental scheme;
(2) Note the process and timeframes of implementing such a scheme;
(3) Agree that a Lane Rental scheme be developed and scheduled to commence with the new Highway maintenance contract in May 2023; and
(4) Delegate authority to the Director of Communities, Economy and Transport to approve the scheme.
· Any works carried out within traffic sensitive days and times will be subject to charges aligned to the cost of disruption. This revenue can be invested back into the highway network to compensate for the disruption caused by the works such as projects to reduce disruption e.g., ducting for easy access without disruption.
· Encourage promotors to complete works to the required standard first time, and with permanent reinstatements, reducing the need to return to the site to carry out remedial works
Other Local Authorities operating a Lane Rental Scheme
2.4 West Sussex County Council (WSCC) and Surrey County Council (SCC) are similarly going through the process of implementing a lane rental scheme. The WSCC Highway Network and Traffic Manager chairs the National Lane Rental Forum, made up of local authority and utility representatives who offer support, guidance and good practice to other local authorities exploring the lane rental scheme. ESCC Officers are liaising with WSCC to learn from their experience.
2.5 The maximum charge under a Lane Rental Scheme is £2,500 per day for each set of works, but Local Authorities can introduce their own proposals to include discounts. For example, Surrey County Council have the following standard lane rental charges
|
Traffic control |
|
Specified location |
Road closure |
Lane closure |
All |
£2,500 |
£1,500 |
“These can be reduced or waived in particular cases such as; collaborating with other works promotors, works that deliver significant infrastructure improvements, works that minimise the impact of future works or extend the longevity of an asset”. Examples of other local authority charging proposals can be found at appendix 1.
2.6 Providing exemptions and reducing associated rental charges to encourage less disruptive working practices will also help to demonstrate to utility companies, and to residents, that lane rental costs are targeted and avoidable and are not simply being employed as a money-raising tool.
Setting up the lane rental scheme
2.8 Approval will be granted on condition that a Permit Scheme is in operation and is seen as ‘best in class’, whereby; Permit fees are proportionate, discounts are offered for joint working, full compliance with regulations and guidance can be shown, and the scheme fully supports the delivery of national infrastructure projects.
2.9 The application for a lane rental scheme must demonstrate that:
2.11 It is expected that implementation of a lane rental scheme will take 16 - 18 months to complete.
3 Financial Considerations
- Investment in innovation and developing new products or disruption-saving techniques and controls. Trials of new techniques and products, installing "pipe subways" or ducting
- Improving the quality or accessibility of records about the location of underground pipes
- Measures to help abate noise, pollution or safety hazards arising as a result of works, repairing potholes caused by utility works; and / or implementing extraordinary measures to mitigate congestion caused by works, especially major works projects.
4.0 Risks
5.1 Cabinet is recommended to note the benefits of introducing a lane rental scheme in East Sussex, as well as the process and timescales set out above and are asked to approve a recommendation to implement a lane rental scheme.
5.2 Subject to Cabinet and DfT approval, it is recommended that the introduction of a lane rental scheme in East Sussex coincides with the start of the new highways maintenance contract in May 2023 and to be administered by the new highway maintenance contractors network management team.
Director of Communities, Economy and Transport
Contact Officer: Dale
Poore
Tel. No. 01273 335506
Email: dale.poore@eastsussex.gov.uk
LOCAL MEMBERS
All Members
BACKGROUND DOCUMENTS
Lane Rental Schemes: Guidance for English Local Highway Authorities
Transport For London Lane Rental Scheme
Kent County Council Lane Rental Scheme
Surrey County Council Lane Rental Scheme
Appendix 1 – Other Local Authority Charging proposals
- West Sussex County Council proposed charges as per consultation in December 2020. Feedback from utility companies, however, has been that they would prefer a simpler charging system so it is likely that the standard £2.500 a day will be charged with discounts applied case by case.
- Kent County Council charges dependent on the banding of the road (KLR = Kent Lane Rental):
-
Band |
Road closure |
Lane closure charge |
KLR1 |
£2,000 |
£800 |
KLR2 |
£2,000 |
£400 |
KLR3 |
£1,600 |
£600 |
KLR4 |
£1,600 |
£300 |
-
-
Appendix 2 – Swift Argent Key Tasks and Milestones for Project Completion
PHASE 1: New Lane Rental Scheme Development & Application
Set up Project Board, meet and send briefings
Cabinet / Committee process confirmed (Approval Stages)
Agree Teletrac TrafficMaster contracts if required
DfT Consultant Access Approval if required
Download AGPS (Aggregated GPS) data
Download Accident Data
Stakeholders notified of intention to submit a proposal
Joint working group established with Terms of Reference (ToR)
Data collection for Lane Rental Scheme Document
Discuss, propose & agree KPI's
Identified suitable streets for charges to apply
Finance discussion before CBA production
Collect data for CBA
Process data for CBA
Undertake Traffic/ Delay Modelling
Draft of objectives for discussion
Agree objectives with stakeholders
Seek EH department agreement
Prepare and agree parity obligation undertaking
Detailed local environmental health considerations
Agree a period of shadow or trial running
Define suitable transitional arrangements
Agree detailed evaluation plan
Dispute resolution process agreed
Draft scheme document production
Prepare a detailed draft Cost Benefit Analysis
Prepare Cost Benefit Analysis Summary
Discuss and agree the draft Cost Benefit Analysis
Prepare proposed charges table
Prepare proposed charges for remedial works
Finance review & approval of charges
Maps of included street prepared
Draft scheme submitted to key stakeholders for review with briefings
Review National Street Gazetteer for suitability (NSG)
Source Current Staffing Levels and Roles
Prepare an impact assessment on the Permit Scheme
Finance review & approval of proposed charges
Finance review & approval of the CBA
Legal review of the Scheme Document before formal consultation period commences
Prepare and Submit Cabinet / Committee Paper (Approval to proceed to consult on
proposals)
Prepare consultation covering letter
Identify consultees
Legal approval of consultation process and covering letter
Formal 12 week consultation period
Consultation workshop
Consultation representations considered
Consultation report prepared
Legal review of formal consultation responses
Final version of documents
DfT Annex A Check List Completed
Prepare SoS Application Pack
Final legal and Senior Officer review of documents and SoS application pack
SoS Application Made
Decision on Go-Live date
IT system review
HR discussion regarding staffing proposals
Cabinet (and others) report seeking approval to implement
Recruitment process begun
Staff accommodation confirmed
IT system work plan
Testing period
Business process workshops
Confirm details of the lane rental team
Confirm contact details for the lane rental team
Pre Go-Live refresher training as part of the ongoing Permit Scheme training
Go-Live
Go-Live support process (online and onsite)
Key Milestones |
Key Schedules to note
|
• Stakeholders notified of intention to submit a proposal • Joint working group established with Terms of Reference • Scheme documents prepared • Proposed streets and charges Identified • Formal consultation undertaken • Internal approvals • Application to SoS • Stakeholder Notice • Shadow Running process • Recruitment process • Go-Live
|
• Formal consultation – 12 weeks duration • SoS application review duration unknown – expect 12 weeks • Statutory notice period – 12 weeks • Shadow Running period – 4 weeks • Recruitment process lead time
|